Temporary Works

Temporary works design for tunnels and metro projects

Bouw Consultants · November 2026 · 4 min read

Launch shafts, thrust frames, deep excavation support, falsework and gantries are temporary — but their failures are permanent. How we design and check them.

Temporary works are the structures that let permanent works be built: launch shafts, thrust frames, struts and anchors, falsework, formwork and gantries. They exist for weeks or months, often carry larger and less predictable loads than the permanent structure, and are built under programme pressure. Many construction collapses worldwide are temporary works failures. Treating them as engineered structures — designed, checked and controlled — is one of the most effective safety measures on any tunnel or metro project.

TBM launching and retrieval

A TBM launch involves a sequence of temporary structures, each with its own load path:

  • Launch shaft — usually diaphragm walls or secant piles with struts or ring beams, sized for the machine, its back-up and the logistics opening;
  • Cradle supporting the shield on the base slab, aligned to the tunnel axis and gradient;
  • Thrust frame and reaction structure carrying the jack forces of the first drive into the shaft wall or base slab — load distribution through the temporary (starter) rings must be checked, including eccentric jack loads;
  • Eye seal and break-out through the shaft wall, often with ground treatment (jet grouting, ground freezing or a soft-eye in the wall) to prevent water and soil inflow.

Retrieval shafts mirror these issues in reverse, with ground treatment behind the reception eye critical in water-bearing ground.

Deep excavation support

Station boxes, shafts and cut-and-cover tunnels rely on embedded walls — diaphragm walls, secant or contiguous piles, sheet piles, or soldier piles with lagging — supported by struts, walers, anchors or top-down slabs. Design uses staged soil–structure analysis that follows the actual excavation and strutting sequence, including:

  • earth and water pressures for each stage, with dewatering and any base-heave or uplift checks;
  • surcharge from cranes, traffic and spoil heaps;
  • strut preload, temperature effects and an accidental strut-removal case;
  • wall deflection and ground settlement, assessed against nearby buildings and utilities.

Instrumentation — inclinometers in walls, strut load cells, piezometers and settlement points — with trigger levels closes the loop between design and site.

Formwork, falsework and lining gantries

Cast-in-place tunnel linings, station slabs and portal structures use formwork and falsework that must resist wet concrete pressure, pour sequence, wind, and eccentric loads. Travelling lining gantries in NATM tunnels need checks for concrete pressure on the shutter skin, stability while travelling, hydraulic support loads, and the stripping time linked to concrete strength. IRC:87 gives Indian guidance for formwork, falsework and temporary structures for road bridges, and the same principles apply underground.

A disciplined process

We recommend the same steps on every project, adapted from BS 5975 practice:

  1. a written design brief agreed with the site team (loads, sequence, plant, interfaces);
  2. design with clear drawings and stated assumptions;
  3. an independent check proportionate to risk;
  4. on-site inspection against the drawings and a permit to load;
  5. a permit to dismantle, because removal stages can be the most dangerous.

For how design responsibility is divided between designer, checker and contractor, read Proof checker responsibility vs contractual obligations. Segment and lining loads from the first TBM drive are discussed in TBM segmental lining design.

Frequently asked questions

What counts as temporary works on a tunnel project?

Any structure needed to build the permanent works and then removed or abandoned: TBM launch and retrieval shafts, thrust frames, cradles and starter rings, excavation support (struts, walers, anchors, sheet or soldier piles), decking, dewatering systems, falsework and formwork, lining gantries, and temporary propping of existing structures.

Does temporary works design need an independent check?

Yes. Many temporary works failures trace back to inadequate design or design that was never checked. Good practice — reflected in BS 5975 and in many Indian contracts — is a design brief, a design, an independent check proportionate to risk, and a formal permit to load and permit to dismantle.

Which loads are most often missed?

Construction plant surcharge near excavations, accidental strut impact, temperature effects on long steel struts, uneven jack forces on TBM thrust frames, and the load cases during each excavation and dismantling stage rather than only the final stage.

Who is responsible for temporary works in an EPC contract?

Usually the contractor, who owns the means and methods. The owner's engineer or proof consultant may review temporary works that affect the permanent works or public safety, but the scope of any review should be written down clearly at the start.