NATM or TBM? Choosing the right tunnelling method

Bouw Consultants · November 2026 · 2 min read

Ground, length, alignment and programme all pull the decision in different directions. Here is how we weigh them at feasibility and pre-bid stage.

Few early decisions shape a tunnel project as strongly as the choice of excavation method. Get it right and the cost, programme and risk profile follow; get it wrong and the project spends years compensating. At feasibility and pre-bid stage we look at the same handful of questions every time.

1. What ground will the tunnel meet?

The New Austrian Tunnelling Method (NATM, also called SEM or SCL) treats the rock mass as part of the support system. Shotcrete, rock bolts and lattice girders are installed close behind the face and adjusted to the ground actually encountered, so it adapts well to variable rock and mixed geology. A TBM is chosen for a ground envelope; if the geology falls far outside it — squeezing ground, large faults, boulders, high water inflow — progress can suffer badly.

2. How long is the drive?

A TBM carries a large up-front cost and mobilisation time. Over long, reasonably uniform drives — typical of urban metro lines — its fast, steady advance more than repays that. For short tunnels, cross passages, caverns, station enlargements and portals, NATM is usually more economical.

3. What sits above the tunnel?

In cities, settlement control is decisive. Closed-face TBMs (EPB or slurry) keep pressure on the face and install a segmental lining immediately behind the shield, giving good control of volume loss beneath buildings and utilities. NATM can also work in urban settings, but needs careful sequencing, ground improvement and real-time monitoring.

4. What shape and size is needed?

A TBM produces a circular section of fixed diameter. NATM can deliver horseshoe shapes, changing sections, junctions and wide spans — useful for road tunnels with lay-bys, crossovers and underground stations.

The answer is often "both"

Many projects combine the methods: TBM running tunnels with NATM cross passages and station tunnels, or NATM in hard rock with cut-and-cover at the portals. What matters is choosing each method for the reason it is good at, and backing that choice with numerical modelling, a realistic risk register and a monitoring plan.