A day on site with a geologist can save months underground. What we check at pre-bid, design and construction stage — and what the site visit report should contain.

Before a single borehole is drilled or a design calculation run, an engineering geologist and a tunnel engineer walking the alignment together will learn more about a project's real risks than any desk study. A focused geological site visit confirms the geological model, identifies hazards at portals and shallow sections, and decides where the investigation money should go.

Prepare before you go

  • regional geological maps and published literature;
  • satellite imagery and a digital elevation model to identify lineaments (possible faults), landslides and drainage lines;
  • the alignment, portal and shaft locations on a topographic base;
  • records of nearby tunnels, quarries, wells and road cuttings;
  • a mapping kit: geological compass, GPS, Schmidt hammer, hand lens, scale, sample bags, camera and — where useful — a drone.

What to check on site

Outcrops and rock mass

Record rock type and weathering grade, and measure every joint set: orientation, spacing, persistence, aperture, roughness and infilling. Unfavourable joint orientations relative to the tunnel axis control wedge failures in the crown and sidewalls, and slope stability at portals.

Faults, shear zones and contacts

Crushed or sheared rock, gouge, slickensides, abrupt changes in rock type and aligned valleys or springs often mark faults. These zones usually govern the worst support classes and the highest water inflows.

Water

Springs, seepage lines, wetlands, streams crossing the alignment and well levels indicate groundwater conditions and potential inflow paths. Water is also a sign of potential loss of supply to local users if the tunnel drains the aquifer.

Portals and slopes

Portals are where shallow, weathered ground meets steep slopes. Look for old landslides, tension cracks, bulging, tilted trees, colluvium thickness and stream erosion at the toe. Portal location changes made at this stage are cheap; made during construction, they are not.

Practical site constraints

Access roads, power, water, space for batching plants and muck disposal, nearby structures and communities, and environmental constraints all affect method and cost.

At pre-bid stage

With limited time, the visit aims to judge whether the tender information is credible, where the main risks lie, and how they should be priced — the proportion of poor ground, likely water, and portal treatment. We combine the visit with a review of the tender's geotechnical data in our pre-bid engineering work.

During construction

Underground, the geological work continues through face mapping of every round, probe drilling ahead of the face and, where needed, seismic prediction ahead of the TBM or NATM face. Comparing predicted and actual conditions and updating the geological model is what lets the NATM design adapt safely.

The site visit report

A useful report contains a geological strip map along the alignment, outcrop data and stereonets, photographs with locations, a preliminary rock mass classification, identified hazards, and a recommended scope for the geotechnical investigation.

Frequently asked questions

When should a geological site visit be carried out?

At least three times: at pre-bid or feasibility stage to judge risk and price; before finalising the investigation and design, to target boreholes and check portal conditions; and during construction, through regular face mapping and visits whenever ground conditions differ from the prediction.

What does a geologist measure at an outcrop?

Rock type and weathering grade; the orientation (dip and dip direction) of each joint set; spacing, persistence, aperture, roughness and infilling of discontinuities; signs of faulting or shearing; seepage; and indicative strength using a Schmidt hammer or point load tests on samples.

Can drones replace a site visit?

No, but they help. Drone photogrammetry and LiDAR give accurate terrain models and allow discontinuities to be mapped on inaccessible slopes. They complement — not replace — direct inspection by an experienced engineering geologist.

What is face mapping?

Face mapping is the geological record of each excavated tunnel face: rock types, discontinuities, water and overbreak, usually with photographs and a classification. In NATM tunnels it is used to confirm or change the support class for the next rounds.